Our Business

Concrete

Back to Projects List Back to Projects List Previous Project Previous Project Next Project Next Project

Sapphire Wind Farm


This project was for the supply and delivery of concrete for 75 wind turbine foundations. 73 foundations were completed within seven months.

The average foundation size was 665m³.

To accomplish this project we had two concrete plants on-site with a combined capacity of 160m³ per hour.

All raw materials were sourced external to the project where possible from local suppliers.

Location

Glen Innes NSW

Industry

Batch Plants

Time frame

2017

Sapphire Wind Farm