This project was for the supply and delivery of concrete for 75 wind turbine foundations. 73 foundations were completed within seven months.
The average foundation size was 665m³.
To accomplish this project we had two concrete plants on-site with a combined capacity of 160m³ per hour.
All raw materials were sourced external to the project where possible from local suppliers.
Glen Innes NSW
Batch Plants
2017