Volume: 215,000 m³.
Scope: Provision of onsite concrete plants for supply of concrete for LNG process plant outside of Port Moresby and Upstream Infrastructure on the Hides gas field.
To meet project requirements Wagners mobilised to the sites 2 X 120m³/hr wet mix plants and 1 X 70m³/hr dry mix plant. All cement was imported into PNG in bags and decanted into bulk storage by Wagners. Wagners also supplied concrete pumping services to the project.
At peak our workforce of 120 included 115 from the local indigenous community who had limited previous concrete production experience and were trained through their employment.
Port Moresby and Hides gas field
Batch Plants
2010 – 2014