Our Business

Our Projects

Back to Projects List Back to Projects List Previous Project Previous Project Next Project Next Project

Chayvo Onshore Gas Processing Facilities


Volume: 30,000 m³.

 

Scope: Provision of onsite concrete plants for supply of concrete for onshore gas processing facilities on Sakhalin Island off the coast of Russia.

 

To meet requirements for this project Wagners mobilised to the site a dry mix plant and associated production and delivery equipment. All raw material storage and concrete production equipment was in an insulated prefabricated shelter with heating for raw materials to allow production in temperatures which dropped to -35 degrees.

 

The closest suitable aggregates for the project were 700 km away and Wagners managed the procurement and delivery to site by train.

Location

Chayvo Sakhalin Island Russia

Industry

Batch Plants

Time frame

2005 - 2008

Chayvo Onshore Gas Processing Facilities